Home > Case Studies > Fencing and Gates for YOI Swinfen Hall

Fencing and Gates for YOI Swinfen Hall

Client

Prince Build

Location

Lichfield

The Background

Since gaining approval as a Ministry of Justice installer, Procter Fencing Systems are proud to announce we have just completed our first high-security prison fencing installation for Prince Build at Swinfen Hall YOI.

The project took us 4 weeks in total to install, this included 5,200 mm HIGH MOJ specification 358 mesh fencing and gates, all posts and razor wire were a free issue by the MOJ. This is clearly a prestigious job and one which is a measure of our standing in the security fencing industry.

The Solution

All the gates were manufactured by Procter Fencing Manufacturing Unit at Astra Park in Leeds which ensured a high standard of quality.

 

The Result or Feedback

This enabled us to achieve our tight deadline and complete all works on time.  The client was satisfied with the final outcome.

We now have experience of the demanding requirements of Prison Service Fencing installations and we are tendering for contracts on other prison’s and YOI and are confident this will be the first of many successful installations.

"Very pleased with the end result and in particular as we gave Procter what seemed like an unrealistic deadline."